United States › Grid › Interconnection queues › Utah

SOLAR + STORAGE · WEST

Solar + storage project Q53, Millard County

Solar + storage project Q53, Millard County is a 570 MW solar + storage request in interconnection study in the West interconnection queue, in Millard County, Utah, connecting to Los Angeles Department of Water and Power.

Queue statusIn planning
  1. PlanningQueued Jul 2016 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2019 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
Q53
Grid region
West (non-ISO utilities)
Utility / transmission owner
Los Angeles Department of Water and Power
Developer
Intermountain Power Agency
Connection point (POI)
IPP 345kV Switchyard
Location
Millard County, Utah
Technology
Solar: 285 MW · Battery: 285 MW
Total requested
570 MW
Study phase
SIS restudy completed. FS finalized. HS finalized. GIA in progress. COD 8/9/27
Queue status
Active
Entered queue
28 July 2016
Proposed online date
June 2019

Location

Marker shows the centre of Millard County; the queue data does not give exact sites.

Power plants in Utah · Transmission lines in Utah

Other requests in Millard County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem