United States › Grid › Interconnection queues › Washington
OTHER · WESTOther project 110, Garfield County
Other project 110, Garfield County is a 560 MW other request in interconnection study in the West interconnection queue, in Garfield County, Washington, connecting to Avista Utilities.
- PlanningQueued Jan 2021 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2025 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 110
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- Avista Utilities
- Connection point (POI)
- DryCreek 230 kV or Walla Walla to Dry Creek 230 kV
- Location
- Garfield County, Washington
- Technology
- Solar: 100 MW · Wind: 275 MW · Battery: 185 MW
- Total requested
- 560 MW
- Service type
- Network resource (NRIS)
- Queue status
- Active
- Entered queue
- 7 January 2021
- Proposed online date
- December 2025
Location
Marker shows the centre of Garfield County; the queue data does not give exact sites.
Power plants in Washington · Transmission lines in Washington
Other requests in Garfield County
- Wind + storage project TCS-14, Garfield CountyWind + storage · 375 MW · under construction
- Onshore wind project G0872, Garfield CountyOnshore wind · 300 MW · in study
- Onshore wind project CS25-11, Garfield CountyOnshore wind · 300 MW · in study
- Lower Snake Phase 1Onshore wind · 150 MW · built
- Solar project G0624, Garfield CountySolar · 1,250 MW · withdrawn
- Other project G0665, Garfield CountyOther · 1,125 MW · withdrawn
- Other project G0730, Garfield CountyOther · 1,125 MW · withdrawn
- Solar + storage project G0824, Garfield CountySolar + storage · 455 MW · withdrawn
- Onshore wind project G0727, Garfield CountyOnshore wind · 300 MW · withdrawn
- Onshore wind project CS23-02, Garfield CountyOnshore wind · 300 MW · withdrawn
- Onshore wind project G0324, Garfield CountyOnshore wind · 300 MW · withdrawn
- Solar + storage project 133, Garfield CountySolar + storage · 300 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem