Solar + storage project Q80, Kern County

Solar + storage project Q80, Kern County is a 590 MW solar + storage request in interconnection study in the West interconnection queue, in Kern County, California, connecting to Los Angeles Department of Water and Power.

Queue statusIn planning
  1. PlanningQueued Apr 2021 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Feb 2024 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
Q80
Grid region
West (non-ISO utilities)
Utility / transmission owner
Los Angeles Department of Water and Power
Connection point (POI)
Barren Ridge 230 kV Sw Station
Location
Kern County, California
Technology
Solar: 350 MW · Battery: 240 MW
Total requested
590 MW
Study phase
Application received
Queue status
Active
Entered queue
7 April 2021
Proposed online date
February 2024

Location

Marker shows the centre of Kern County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Kern County