United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Interconnection queue in the USA — page 9

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown9,1872,001.0 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

9,187 requests · page 9 of 184
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project Company MI, Churchill County
Solar + storage
700 MWAgreement signed Churchill, NVWest Sep 2021target 2024
Kawich
Solar + storage
700 MWAgreement signed Clark, NVCAISO Apr 2021target 2029
Solar + storage project Q94, Millard County
Solar + storage · Intermountain Power Agency
700 MWIn study Millard, UTWest Dec 2022target 2026
Solar project AH2-348, Daviess County
Solar
700 MWIn study Daviess, INPJM Mar 2022target 2025
Solar + storage project Q401, Coconino County
Solar + storage
700 MWIn study Coconino, AZWest Sep 2021target 2026
Solar + storage project 93, Apache County
Solar + storage
700 MWIn study Apache, AZWest Apr 2021target 2021
Solar project J2846, Pulaski County
Solar
700 MWIn study Pulaski, INMISO Sep 2022target 2025
Cedar Bayou 5 (TEF - Due Diligence)
Gas · NRG Cedar Bayou 5 LLC
697 MWAgreement signed Chambers, TXERCOT Mar 2020target 2027
Gas project 25RSC-001, Fayette County
Gas
692 MWIn study Fayette, TNSoutheast Jul 2025target 2031
Gas project LGE-GIS-2013-001, Jefferson County
Gas
691 MWAgreement signed Jefferson, KYSoutheast Aug 2013target 2015
Gas project GEN-2024-128, Caddo County
Gas
690 MWIn study Caddo, OKSPP Mar 2025target 2030
Gas project LGE-GIS-2010-001, Jefferson County
Gas
690 MWAgreement signed Jefferson, KYSoutheast Apr 2010target 2015
Solar + storage project Q114, Juab County
Solar + storage · Intermountain Power Agency
690 MWIn study Juab, UTWest Aug 2025target 2029
Gas project GI-2011-4, Denver County
Gas
687 MWAgreement signed Denver, COWest Apr 2011target 2015
Gas project IC-1158, Mobile County
Gas
685 MWPaused / redesign Mobile, ALSoutheast Aug 2023target 2028
Menifee Power Bank
Battery storage
680 MWAgreement signed Riverside, CACAISO Apr 2019target 2025
Gas project LGE-CS2025-002, Jefferson County
Gas
680 MWIn study Jefferson, KYSoutheast Nov 2025target 2031
Texpo
Gas · Oklaunion Power Station, LLC
680 MWIn study Wilbarger, TXERCOT Mar 2021target 2027
Steel City Battery Storage
Battery storage
675 MWAgreement signed Contra Costa, CACAISO Apr 2020target 2029
Solar + storage project AH1-552, Prince George's County
Solar + storage · Chalk Point Steam, LLC
670 MWIn study Prince George's, MDPJM Mar 2025target 2025
Gas project G0752, Morrow County
Gas
670 MWIn study Morrow, ORWest Jun 2022target 2025
Other project G1072, Lewis County
Other
667 MWIn study Lewis, WAWest Dec 2024target 2027
Dovetail Solar 3
Solar + storage · Hecate Energy Dovetail Solar Holdings LLC
666 MWIn study Jack, TXERCOT Dec 2021target 2029
Dovetail Solar 1
Solar + storage · Hecate Energy Dovetail Solar 1 LLC
666 MWIn study Jack, TXERCOT Sep 2021target 2027
Dovetail Solar 2
Solar + storage · Hecate Energy Dovetail Solar 2 LLC
666 MWIn study Jack, TXERCOT Oct 2021target 2029
Gas project J4159, Ottawa County
Gas
664 MWIn study Ottawa, MIMISO Aug 2025target 2028
Gas project LGE-GIS-2022-003, Jefferson County
Gas
660 MWAgreement signed Jefferson, KYSoutheast Jun 2022target 2027
Jack County III – 345 kV
Gas · Jack County Power Development, LLC
660 MWIn study Jack, TXERCOT Nov 2023target 2027
Gas project LGE-GIS-2023-002, Mercer County
Gas
660 MWAgreement signed Mercer, KYSoutheast Apr 2023target 2030
Sunrise Power Improvement
Gas
656 MWIn study Kern, CACAISO Apr 2020target 2024
Coleto Creek - Fuel Change Only
Gas · COLETO CREEK POWER LLC
655 MWIn study Goliad, TXERCOT Apr 2025target 2026
Pinnington Solar
Solar + storage · Hecate Energy Longhorn Solar LLC
654 MWAgreement signed Jack, TXERCOT Dec 2020target 2026
Battery storage project AH1-716, James City County
Battery storage · Cardinal Energy Storage East, LLC
650 MWIn study James City, VAPJM Apr 2025
Battery storage project G1056, Deschutes County
Battery storage
650 MWIn study Deschutes, ORWest Nov 2023target 2030
Battery storage project G0963, Morrow County
Battery storage
650 MWIn study Morrow, ORWest Oct 2023target 2030
Battery storage project G0948, Sherman County
Battery storage
650 MWIn study Sherman, ORWest Oct 2023target 2028
Battery storage project G0947, Sherman County
Battery storage
650 MWIn study Sherman, ORWest Oct 2023target 2028
Battery storage project G0796, Sherman County
Battery storage
650 MWIn study Sherman, ORWest Aug 2022target 2029
Battery storage project G0778, Umatilla County
Battery storage
650 MWIn study Umatilla, ORWest Aug 2022target 2027
Gas project J3604, Sullivan County
Gas
650 MWIn study Sullivan, INMISO Apr 2024target 2027
Battery storage project G0965, Umatilla County
Battery storage
650 MWIn study Umatilla, ORWest Oct 2023target 2032
Battery storage project G0774, Wasco County
Battery storage
650 MWIn study Wasco, ORWest Aug 2022target 2028
Battery storage project G0946, Sherman County
Battery storage
650 MWIn study Sherman, ORWest Oct 2023target 2028
Battery storage project G0792, Sherman County
Battery storage
650 MWIn study Sherman, ORWest Aug 2022target 2029
Solar + storage project GEN-2020-007, Linn County
Solar + storage
650 MWAgreement signed Linn, KSSPP Apr 2020target 2028
Nuclear project J3932, Linn County
Nuclear
646 MWIn study Linn, IAMISO Mar 2025target 2029
Hydro project G0566, Lincoln County
Hydro
646 MWIn study Lincoln, MTWest Jun 2017target 2022
Gas project JEA-Q008, Duval County
Gas
645 MWIn study Duval, FLSoutheast Feb 2018target 2030
Gas project J3084, Sullivan County
Gas
642 MWIn study Sullivan, INMISO Aug 2025target 2026
Commodus 2 Wind
Onshore wind · IP Blackwell II, LLC
642 MWIn study Swisher, TXERCOT Mar 2025target 2029
Page 9 of 184

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)