Solar + storage project Q114, Juab County

Solar + storage project Q114, Juab County is a 690 MW solar + storage request in interconnection study in the West interconnection queue, in Juab County, Utah, connecting to Los Angeles Department of Water and Power.

Queue statusIn planning
  1. PlanningQueued Aug 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Oct 2029 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
Q114
Grid region
West (non-ISO utilities)
Utility / transmission owner
Los Angeles Department of Water and Power
Developer
Intermountain Power Agency
Connection point (POI)
IPP 345kV Mona Tie Line
Location
Juab County, Utah
Technology
Solar: 345 MW · Battery: 345 MW
Total requested
690 MW
Study phase
Application received
Queue status
Active
Entered queue
9 August 2025
Proposed online date
October 2029

Location

Marker shows the centre of Juab County; the queue data does not give exact sites.

Power plants in Utah · Transmission lines in Utah

Other requests in Juab County