United States › Grid › Interconnection queues › Maryland
SOLAR + STORAGE · PJMSolar + storage project AH1-552, Prince George's County
Solar + storage project AH1-552, Prince George's County is a 670 MW solar + storage request in interconnection study in the PJM interconnection queue, in Prince George's County, Maryland, connecting to PEPCO.
- PlanningQueued Mar 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jun 2025 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- AH1-552
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- PEPCO
- Developer
- Chalk Point Steam, LLC
- Connection point (POI)
- Chalk Point units 1 and 2 (the retired coal plant)
- Location
- Prince George's County, Maryland
- Technology
- Solar: 670 MW · Battery
- Total requested
- 670 MW
- Service type
- Network resource (NRIS)
- Study phase
- System Impact Study
- Queue status
- Active
- Entered queue
- 4 March 2025
- Proposed online date
- June 2025
Location
Marker shows the centre of Prince George's County; the queue data does not give exact sites.
Other requests in Prince George's County
- Battery storage project AH2-332, Prince George's CountyBattery storage · 115 MW · in study
- Gas project AH1-744, Prince George's CountyGas · 53.5 MW · in study
- Gas project AH2-269A, Prince George's CountyGas · 45.0 MW · in study
- Solar project AH2-065, Prince George's CountySolar · 2.0 MW · in study
- Keys Energy CenterGas · 736 MW · built
- Keys Energy CenterGas · 64.5 MW · built
- Chalk PointGas · 6.0 MW · built
- Spectrum SolarSolar · 5.6 MW · built
- Other project H20, Prince George's CountyOther · 3.5 MW · built
- Rollins Avenue PhoenixSolar · 2.5 MW · built
- Chalk Point CT 2Gas · 2.0 MW · built
- Mattawoman EnergyGas · 894 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem