United States › Grid › Interconnection queues › Maryland

GAS · PJM

Keys Energy Center

Keys Energy Center is a 736 MW gas request built and operating in the PJM interconnection queue, in Prince George's County, Maryland, connecting to PEPCO.

Queue statusOperating
  1. PlanningQueued Jan 2012 (completed)
  2. ConsentedApr 2014 (completed)
  3. Construction (completed)
  4. OperatingMay 2018 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
X4-035
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PEPCO
Connection point (POI)
Burches Hill-Chalk Point 500kV
Location
Prince George's County, Maryland
Technology
Gas: 736 MW
Total requested
736 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Operational
Entered queue
20 January 2012
Agreement signed
18 April 2014
Proposed online date
June 2018
Came online
May 2018

Location

Marker shows the centre of Prince George's County; the queue data does not give exact sites.

Power plants in Maryland · Transmission lines in Maryland

Other requests in Prince George's County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem