United States › Grid › Interconnection queues › Maryland
GAS · PJMKeys Energy Center
Keys Energy Center is a 64.5 MW gas request built and operating in the PJM interconnection queue, in Prince George's County, Maryland, connecting to PEPCO.
Request details
- Queue ID
- Z1-052
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- PEPCO
- Connection point (POI)
- Burches Hill-Chalk Point 500kV
- Location
- Prince George's County, Maryland
- Technology
- Gas: 64.5 MW
- Total requested
- 64.5 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
- Queue status
- Operational
- Entered queue
- 29 August 2013
- Proposed online date
- August 2018
- Came online
- July 2018
Location
Marker shows the centre of Prince George's County; the queue data does not give exact sites.
Other requests in Prince George's County
- Solar + storage project AH1-552, Prince George's CountySolar + storage · 670 MW · in study
- Battery storage project AH2-332, Prince George's CountyBattery storage · 115 MW · in study
- Gas project AH1-744, Prince George's CountyGas · 53.5 MW · in study
- Gas project AH2-269A, Prince George's CountyGas · 45.0 MW · in study
- Solar project AH2-065, Prince George's CountySolar · 2.0 MW · in study
- Keys Energy CenterGas · 736 MW · built
- Chalk PointGas · 6.0 MW · built
- Spectrum SolarSolar · 5.6 MW · built
- Other project H20, Prince George's CountyOther · 3.5 MW · built
- Rollins Avenue PhoenixSolar · 2.5 MW · built
- Chalk Point CT 2Gas · 2.0 MW · built
- Mattawoman EnergyGas · 894 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem