Chalk Point

Chalk Point is a 6.0 MW gas request built and operating in the PJM interconnection queue, in Prince George's County, Maryland, connecting to PEPCO.

Queue statusOperating
  1. PlanningQueued Jan 2001 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingMar 2001 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
F08
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PEPCO
Connection point (POI)
Chalk Point 230kV
Location
Prince George's County, Maryland
Technology
Gas: 6.0 MW
Total requested
6.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
Queue status
Operational
Entered queue
31 January 2001
Proposed online date
March 2001
Came online
March 2001

Location

Marker shows the centre of Prince George's County; the queue data does not give exact sites.

Power plants in Maryland · Transmission lines in Maryland

Other requests in Prince George's County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem