United States › Grid › Interconnection queues
OCTARY USA · INTERCONNECTION QUEUESInterconnection queue in the USA — page 160
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Solar + storage project AH2-242, Montgomery County Solar + storage |
45.0 MW | In study |
| Solar project Q346, Maricopa County Solar |
45.0 MW | Paused / redesign |
| Nuclear project 788, Bingham County Nuclear |
45.0 MW | In study |
| Battery storage project J1882, Tazewell County Battery storage |
45.0 MW | In study |
| Battery storage project AH2-241, City Of Chesapeake County Battery storage |
45.0 MW | In study |
| Waller Solar I Solar |
45.0 MW | Agreement signed |
| Gas project AH2-269A, Prince George's County Gas |
45.0 MW | In study |
| Battery storage project AI2-277, Greensville County Battery storage |
45.0 MW | In study |
| Solar + storage project C1-10, Emery County Solar + storage · Emery Bull Creek Energy, LLC |
45.0 MW | Paused / redesign |
| Battery storage project J1861, Laporte County Battery storage |
45.0 MW | In study |
| Geothermal project Company HN, Washoe County Geothermal |
45.0 MW | Agreement signed |
| Glen Falls Facility Gas |
45.0 MW | Agreement signed |
| West Springfield 45 MW BESS Battery storage |
45.0 MW | Agreement signed |
| Solar + storage project AH2-344, Marion County Solar + storage |
45.0 MW | In study |
| Solar + storage project 862, Box Elder County Solar + storage · Rocket Solar, LLC |
45.0 MW | Paused / redesign |
| Solar project AH2-166, Fulton County Solar |
45.0 MW | In study |
| Waller Solar I Solar |
45.0 MW | Agreement signed |
| Sword BESS Solar + storage · Hidalgo Solar LLC |
44.4 MW | In study |
| Solar project AI2-150, Huntington County Solar |
44.4 MW | In study |
| Solar + storage project J1201, Montgomery County Solar + storage |
44.2 MW | Agreement signed |
| Ares Nevada Battery storage |
44.0 MW | Agreement signed |
| Sunrise Wind II Offshore wind · Sunrise Wind LLC |
44.0 MW | In study |
| Solar project 920663, Randolph County Solar |
44.0 MW | In study |
| Solar project IC-1203, Jasper County Solar |
44.0 MW | Agreement signed |
| Horse13 CallD repower Onshore wind · Nextera |
44.0 MW | Agreement signed |
| Coal project 12-047, Morrow County Coal |
44.0 MW | Paused / redesign |
| Peach Bottom Units #2 & #3 Nuclear |
44.0 MW | Agreement signed |
| Solar + storage project AH2-028, Pickaway County Solar + storage |
44.0 MW | In study |
| HHGT repower Horse13+CallD Onshore wind · Nextera |
44.0 MW | Agreement signed |
| Electric E - West Texas Generation Gas · Electric E Power Marketing |
43.6 MW | In study |
| Solar project AI2-159, Miami County Solar |
43.5 MW | In study |
| Graphic Packaging Gas Gas · Graphic Packaging International |
43.4 MW | In study |
| Solar project AI2-421, Dekalb County Solar |
43.2 MW | In study |
| Solar project AI2-426, Allen County Solar |
43.2 MW | In study |
| Old Sorrell Energy Storage Battery storage |
43.1 MW | Paused / redesign |
| Other project Q550, Maricopa County Other |
43.0 MW | In study |
| Hector Storage Solar + storage · Hector Solar, LLC |
42.7 MW | In study |
| Braswell Solar Solar · Gransolar Texas Nine, LLC |
42.6 MW | In study |
| Pamplona Solar Solar + storage · Karol Solar III |
42.4 MW | In study |
| Gas project IA-PNM-2013-01, Valencia County Gas |
42.3 MW | Agreement signed |
| Solar project J4150, Cass County Solar |
42.2 MW | In study |
| Air Station 1 Solar + storage |
42.1 MW | In study |
| Other project Q549, Maricopa County Other |
42.1 MW | In study |
| Onshore wind project C2-12, Converse County Onshore wind · PacifiCorp |
42.0 MW | Agreement signed |
| Solar project 39, Orangeburg County Solar |
42.0 MW | Under construction |
| Vinton Energy Storage Battery storage |
42.0 MW | Paused / redesign |
| Solar + storage project 562, Malheur County Solar + storage · Moores Hollow PV1, LLC |
42.0 MW | Paused / redesign |
| Solar + storage project GEN-2024-052, Choctaw County Solar + storage |
42.0 MW | In study |
| Solar project J2756, Livingston County Solar |
42.0 MW | In study |
| Solar project GEN-2021-SR8, Harper County Solar |
42.0 MW | Agreement signed |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)1,857 · 519.1 GW
- ERCOT (Texas)1,986 · 447.3 GW
- MISO (Midcontinent)1,646 · 350.1 GW
- CAISO (California)429 · 188.6 GW
- Southeast (non-ISO utilities)1,067 · 161.4 GW
- SPP (Southwest Power Pool)692 · 152.4 GW
- PJM (Mid-Atlantic, Midwest)1,248 · 140.4 GW
- NYISO (New York)190 · 27.1 GW
- ISO-NE (New England)72 · 14.6 GW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)