Solar + storage project 862, Box Elder County

Solar + storage project 862, Box Elder County is a 45.0 MW solar + storage request suspended in the West interconnection queue, in Box Elder County, Utah, connecting to PacifiCorp.

Queue statusPaused / redesign
  1. PlanningQueued Apr 2017 (current stage)
  2. ConsentedFeb 2020 (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2019 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
862
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Developer
Rocket Solar, LLC
Connection point (POI)
Lampo substation
Location
Box Elder County, Utah
Technology
Solar: 45.0 MW · Battery
Total requested
45.0 MW
Service type
Energy only (ERIS)
Study phase
IA executed 2/11/20, suspended 3/17/23
Queue status
Suspended
Entered queue
6 April 2017
Agreement signed
11 February 2020
Proposed online date
June 2019

Location

Marker shows the centre of Box Elder County; the queue data does not give exact sites.