🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Utah

SOLAR · WEST

Solar project 1030, Box Elder County

Solar project 1030, Box Elder County is a 2.0 MW solar request built and operating in the West interconnection queue, in Box Elder County, Utah, connecting to PacifiCorp.

Queue statusOperating
  1. PlanningQueued May 2018 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingTarget Nov 2018 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
1030
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Developer
Nucor Corporation
Connection point (POI)
Cutler-El Monte Vulcraft Tap transmission line
Location
Box Elder County, Utah
Technology
Solar: 2.0 MW
Total requested
2.0 MW
Service type
Energy only (ERIS)
Study phase
IA executed 10/9/2018
Queue status
Operational
Entered queue
29 May 2018
Proposed online date
November 2018

Location

Marker shows the centre of Box Elder County; the queue data does not give exact sites.

Power plants in Utah · Transmission lines in Utah

Other requests in Box Elder County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem