United States › Grid › Interconnection queues › Utah

SOLAR + STORAGE · WEST

Solar + storage project 754, Box Elder County

Solar + storage project 754, Box Elder County is a 80.0 MW solar + storage request with a signed interconnection agreement in the West interconnection queue, in Box Elder County, Utah, connecting to PacifiCorp.

Queue statusConsented
  1. PlanningQueued May 2016 (completed)
  2. ConsentedJun 2018 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2023 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
754
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Developer
Steel Solar, LLC
Connection point (POI)
Wheelon-Nucor transmission line
Location
Box Elder County, Utah
Technology
Solar: 80.0 MW · Battery
Total requested
80.0 MW
Service type
Energy only (ERIS)
Study phase
IA signed 6/28/18
Queue status
Active
Entered queue
25 May 2016
Agreement signed
28 June 2018
Proposed online date
June 2023

Location

Marker shows the centre of Box Elder County; the queue data does not give exact sites.

Power plants in Utah · Transmission lines in Utah

Other requests in Box Elder County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem