🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Virginia

SOLAR · PJM

Waller Solar I

Waller Solar I is a 45.0 MW solar request with a signed interconnection agreement in the PJM interconnection queue, in Lancaster County, Virginia, connecting to Dominion.

Queue statusConsented
  1. PlanningQueued Jun 2020 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
AG1-038
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
Dominion
Connection point (POI)
Garner DP-Lancaster 115 kV
Location
Lancaster County, Virginia
Technology
Solar: 45.0 MW
Total requested
45.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
Queue status
Active
Entered queue
16 June 2020
Proposed online date
December 2027

Location

Marker shows the centre of Lancaster County; the queue data does not give exact sites.

Power plants in Virginia · Transmission lines in Virginia

Other requests in Lancaster County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem