NUCLEAR · PJM

Peach Bottom Units #2 & #3

Peach Bottom Units #2 & #3 is a 44.0 MW nuclear request with a signed interconnection agreement in the PJM interconnection queue, in York County, Pennsylvania, connecting to PECO.

Queue statusConsented
  1. PlanningQueued Apr 2016 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingMar 2019 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
AB2-175
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PECO
Connection point (POI)
Peach Bottom 500kV
Location
York County, Pennsylvania
Technology
Nuclear: 44.0 MW
Total requested
44.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
Queue status
Active
Entered queue
29 April 2016
Proposed online date
December 2018
Came online
March 2019

Location

Marker shows the centre of York County; the queue data does not give exact sites.

Power plants in Pennsylvania · Transmission lines in Pennsylvania

Other requests in York County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem