United States › Grid › Interconnection queues › Oregon
SOLAR + STORAGE · WESTSolar + storage project 562, Malheur County
Solar + storage project 562, Malheur County is a 42.0 MW solar + storage request suspended in the West interconnection queue, in Malheur County, Oregon, connecting to Idaho Power Company.
Queue statusPaused / redesign
- PlanningQueued Aug 2019 (current stage)
- ConsentedAug 2021 (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2024 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 562
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- Idaho Power Company
- Developer
- Moores Hollow PV1, LLC
- Connection point (POI)
- ONTO–WEJN 138kV Line
- Location
- Malheur County, Oregon
- Technology
- Solar: 42.0 MW · Battery
- Total requested
- 42.0 MW
- Service type
- Other
- Study phase
- IA Executed
- Queue status
- Suspended
- Entered queue
- 5 August 2019
- Agreement signed
- 31 August 2021
- Proposed online date
- December 2024
Location
Marker shows the centre of Malheur County; the queue data does not give exact sites.
Other requests in Malheur County
- Battery storage project 622, Malheur CountyBattery storage · 600 MW · agreement signed
- Solar project 752, Malheur CountySolar · 4.2 MW · agreement signed
- Geothermal project 179, Malheur CountyGeothermal · 36.0 MW · built
- Solar project 424, Malheur CountySolar · 10.0 MW · built
- Solar project 413, Malheur CountySolar · 10.0 MW · built
- Solar project 412, Malheur CountySolar · 10.0 MW · built
- Solar project 419, Malheur CountySolar · 9.0 MW · built
- Other project hist_q70, Malheur CountyOther · 7.0 MW · built
- Solar project 414, Malheur CountySolar · 6.0 MW · built
- Other project OYDM, Malheur CountyOther · 5.0 MW · built
- Solar project 425, Malheur CountySolar · 4.5 MW · built
- Solar project 525, Malheur CountySolar · 3.0 MW · built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem