SOLAR + STORAGE · PJMSolar + storage project AH2-344, Marion County
Solar + storage project AH2-344, Marion County is a 45.0 MW solar + storage request in interconnection study in the PJM interconnection queue, in Marion County, Ohio, connecting to AEP.
Queue statusIn planning
- PlanningQueued Mar 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Mar 2025 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- AH2-344
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Connection point (POI)
- La Rue 138 kV
- Location
- Marion County, Ohio
- Technology
- Solar: 45.0 MW · Battery
- Total requested
- 45.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Feasibility Study
- Queue status
- Active
- Entered queue
- 10 March 2022
- Proposed online date
- March 2025
Location
Marker shows the centre of Marion County; the queue data does not give exact sites.
Other requests in Marion County
- Marion County Solar ProjectSolar · 100 MW · agreement signed
- Green Camp Solar IISolar + storage · 110 MW · in study
- Solar project AG2-119, Marion CountySolar · 80.0 MW · in study
- Solar project AI2-341, Marion CountySolar · 22.8 MW · in study
- Solar + storage project AI1-175, Marion CountySolar + storage · 19.5 MW · in study
- Chestnut SolarSolar · 60.0 MW · suspended
- Onshore wind project X3-030, Marion CountyOnshore wind · 245 MW · withdrawn
- Solar project AB2-131, Marion CountySolar · 150 MW · withdrawn
- Solar project AG2-595, Marion CountySolar · 65.0 MW · withdrawn
- Solar project AG2-218, Marion CountySolar · 49.5 MW · withdrawn
- Solar project AH1-572, Marion CountySolar · 30.0 MW · withdrawn
- Solar project AH1-075, Marion CountySolar · 24.7 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem