πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Ohio

SOLAR Β· PJM

Chestnut Solar

Chestnut Solar is a 60.0 MW solar request suspended in the PJM interconnection queue, in Marion County, Ohio, connecting to AEP.

Queue statusPaused / redesign
  1. PlanningQueued Sep 2017 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
AD1-106
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
North Waldo-Wild Creek 138 kV
Location
Marion County, Ohio
Technology
Solar: 60.0 MW
Total requested
60.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Suspended
Entered queue
23 September 2017
Proposed online date
December 2026

Location

Marker shows the centre of Marion County; the queue data does not give exact sites.

Power plants in Ohio Β· Transmission lines in Ohio

Other requests in Marion County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem