SOLAR + STORAGE · PJM

Solar + storage project AI1-175, Marion County

Solar + storage project AI1-175, Marion County is a 19.5 MW solar + storage request in interconnection study in the PJM interconnection queue, in Marion County, Ohio, connecting to AEP.

Queue statusIn planning
  1. PlanningQueued Sep 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2024 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
AI1-175
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
Waldo - North Waldo 69 kV
Location
Marion County, Ohio
Technology
Solar: 19.5 MW · Battery
Total requested
19.5 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Active
Entered queue
9 September 2022
Proposed online date
December 2024

Location

Marker shows the centre of Marion County; the queue data does not give exact sites.

Power plants in Ohio · Transmission lines in Ohio

Other requests in Marion County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem