πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Ohio

ONSHORE WIND Β· PJM

Onshore wind project X3-030, Marion County

Onshore wind project X3-030, Marion County is a 245 MW onshore wind request withdrawn in the PJM interconnection queue, in Marion County, Ohio, connecting to Dayton.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2011 (completed)
  2. Withdrawn / abandonedMay 2013 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
X3-030
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
Dayton
Connection point (POI)
Shelby-S.W. Lima 345kV
Location
Marion County, Ohio
Technology
Wind: 245 MW
Total requested
245 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study
Queue status
Withdrawn
Entered queue
30 August 2011
Proposed online date
December 2015
Withdrawn
May 2013

Location

Marker shows the centre of Marion County; the queue data does not give exact sites.

Power plants in Ohio Β· Transmission lines in Ohio

Other requests in Marion County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem