United States › Grid › Interconnection queues › Illinois
SOLAR + STORAGE · MISOSolar + storage project J1201, Montgomery County
Solar + storage project J1201, Montgomery County is a 44.2 MW solar + storage request with a signed interconnection agreement in the MISO interconnection queue, in Montgomery County, Illinois, connecting to AMEREN ILLINOIS.
Queue statusConsented
- PlanningQueued Apr 2019 (completed)
- ConsentedDec 2024 (current stage)
- Construction (not yet reached)
- OperatingTarget Jun 2024 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- J1201
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- AMEREN ILLINOIS
- Connection point (POI)
- North Coffeen 138kV Substation
- Location
- Montgomery County, Illinois
- Technology
- Solar: 44.2 MW · Battery
- Total requested
- 44.2 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA; Post GIA Status: Not Started
- Queue status
- Active
- Entered queue
- 25 April 2019
- Agreement signed
- 11 December 2024
- Proposed online date
- June 2024
Location
Marker shows the centre of Montgomery County; the queue data does not give exact sites.
Other requests in Montgomery County
- Solar project J3556, Montgomery CountySolar · 250 MW · in study
- Battery storage project J2607, Montgomery CountyBattery storage · 200 MW · in study
- Solar project J2334, Montgomery CountySolar · 195 MW · in study
- Solar project J2937, Montgomery CountySolar · 186 MW · in study
- Coal project G806, Montgomery CountyCoal · 19.0 MW · built
- Onshore wind project J205, Montgomery CountyOnshore wind · 200 MW · withdrawn
- Solar project J463, Montgomery CountySolar · 200 MW · withdrawn
- Solar project J1324, Montgomery CountySolar · 150 MW · withdrawn
- Onshore wind project G915, Montgomery CountyOnshore wind · 150 MW · withdrawn
- Other project J2196, Montgomery CountyOther · 100 MW · withdrawn
- Solar project J3507, Montgomery CountySolar · 17.0 MW · withdrawn
- Solar project J882, Montgomery CountySolar · 15.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem