ONSHORE WIND Β· MISO

Onshore wind project J205, Montgomery County

Onshore wind project J205, Montgomery County is a 200 MW onshore wind request withdrawn in the MISO interconnection queue, in Montgomery County, Illinois.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2011 (completed)
  2. Withdrawn / abandonedNov 2011 (project stopped here)
  3. ConsentedNov 2011 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J205
Grid region
MISO (Midcontinent)
Connection point (POI)
Pana - Midway 138kV
Location
Montgomery County, Illinois
Technology
Wind: 200 MW
Total requested
200 MW
Study phase
Feasibility
Queue status
Withdrawn
Entered queue
17 February 2011
Agreement signed
21 November 2011
Proposed online date
September 2012
Withdrawn
November 2011

Location

Marker shows the centre of Montgomery County; the queue data does not give exact sites.