🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › New York

OFFSHORE WIND · NYISO

Sunrise Wind II

Sunrise Wind II is a 44.0 MW offshore wind request in interconnection study in the NYISO interconnection queue, in Suffolk County, New York, connecting to LIPA.

Queue statusIn planning
  1. PlanningQueued Jan 2020 (current stage)
  2. ConsentedJan 2023 (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jul 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
987
Grid region
NYISO (New York)
Utility / transmission owner
LIPA
Developer
Sunrise Wind LLC
Connection point (POI)
Holbrook 138kV
Location
Suffolk County, New York
Technology
Offshore Wind: 44.0 MW
Total requested
44.0 MW
Study phase
FS
Queue status
Active
Entered queue
29 January 2020
Agreement signed
11 January 2023
Proposed online date
July 2027

Location

Marker shows the centre of Suffolk County; the queue data does not give exact sites.

Power plants in New York · Transmission lines in New York

Other requests in Suffolk County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem