United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Interconnection queue in the USA — page 37

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown9,1872,001.0 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

9,187 requests · page 37 of 184
ProjectCapacityStatusLocationRegionQueuedOnline
Other project Q597, Yuma County
Other
300 MWIn study Yuma, AZWest May 2025target 2029
Wind + storage project J3468, Day County
Wind + storage
300 MWIn study Day, SDMISO Apr 2024target 2028
Onshore wind project T2-025, Bingham County
Onshore wind
300 MWIn study Bingham, IDWest Sep 2025target 2030
Solar + storage project Company MA, White Pine County
Solar + storage
300 MWAgreement signed White Pine, NVWest Sep 2021target 2028
Onshore wind project GEN-2024-142, Mcpherson County
Onshore wind
300 MWIn study Mcpherson, KSSPP Mar 2025target 2031
Gas project GEN-2024-253, Leavenworth County
Gas
300 MWIn study Leavenworth, KSSPP Mar 2025target 2027
Battery Storage
Battery storage
300 MWIn study Norfolk, MAISO-NE Mar 2022target 2028
Macadamia Solar
Solar
300 MWAgreement signed Washington, NCPJM Sep 2017target 2028
Onshore wind project GEN-2017-014, Haakon County
Onshore wind
300 MWAgreement signed Haakon, SDSPP May 2017target 2027
Willard Storage
Battery storage · Emeren US, LLC
300 MWIn study Rensselaer, NYNYISO Sep 2024target 2028
Battery storage project AI1-017, Surry County
Battery storage
300 MWIn study Surry, VAPJM Apr 2022target 2026
Onshore wind project J2613, Jackson County
Onshore wind
300 MWIn study Jackson, ARMISO Sep 2022target 2025
Battery storage project GenRep1, Berkeley County
Battery storage · Santee Cooper
300 MWIn study Berkeley, SCSoutheast Nov 2025target 2027
Other project GI-CS-2025-29, Yuma County
Other
300 MWIn study Yuma, COWest Oct 2025target 2031
Onshore wind project BHBE G13, Custer County
Onshore wind
300 MWAgreement signed Custer, NEWest Jul 2017target 2023
Photo Solar 2
Solar + storage · CED Development Inc.
300 MWIn study Uvalde, TXERCOT Sep 2022target 2027
Battery storage project AH2-334, Camden County
Battery storage
300 MWIn study Camden, NJPJM Mar 2022target 2025
Onshore wind project J3886, Swift County
Onshore wind
300 MWIn study Swift, MNMISO Feb 2025target 2030
Arroyo Del Bisonte Solar
Solar · Sunchase Power
300 MWPaused / redesign Wharton, TXERCOT May 2018target 2021
Mammoth Central II Energy Center
Solar
300 MWAgreement signed Pulaski, INPJM Sep 2020target 2028
Solar project J1058, Lake County
Solar
300 MWUnder construction Lake, INMISO Mar 2018target 2024
Pierce Wind
Onshore wind
300 MWPaused / redesign Wharton, TXERCOT Jan 2018
Solar + storage project 2023-G17, Mohave County
Solar + storage
300 MWIn study Mohave, AZWest Dec 2023target 2027
Solar project J3412, Ford County
Solar
300 MWIn study Ford, ILMISO Mar 2024target 2028
Solar + storage project IA-PNM-2021-10, Bernalillo County
Solar + storage · NextEra Energy
300 MWAgreement signed Bernalillo, NMWest Jul 2021target 2025
Other project Q586, Maricopa County
Other
300 MWIn study Maricopa, AZWest May 2025target 2030
Other project PP00041, Wake County
Other
300 MWIn study Wake, NCSoutheast Aug 2025target 2030
Battery storage project AH2-415, Livingston County
Battery storage
300 MWIn study Livingston, ILPJM Mar 2022target 2026
Coal project BHBE G4, Campbell County
Coal · Basin Electric
300 MWAgreement signed Campbell, SDWest Jan 2005target 2011
Onshore wind project GEN-2021-056, Harper County
Onshore wind
300 MWAgreement signed Harper, KSSPP Apr 2021target 2030
Battery storage project GEN-2024-339, Leavenworth County
Battery storage
300 MWIn study Leavenworth, KSSPP Mar 2025target 2029
Onshore wind project Company LF, Lassen County
Onshore wind
300 MWPaused / redesign Lassen, CAWest Mar 2021target 2023
Solar + storage project GI-DISIS-2021-11, Las Animas County
Solar + storage
300 MWPaused / redesign Las Animas, COWest May 2021target 2026
Solar + storage project Q443, Yuma County
Solar + storage
300 MWIn study Yuma, AZWest Mar 2022target 2027
Other project G0925, Walla Walla County
Other
300 MWIn study Walla Walla, WAWest Sep 2023target 2027
Onshore wind project Q86, Millard County
Onshore wind · Intermountain Power Agency
300 MWIn study Millard, UTWest Nov 2021target 2025
Gas project PIS040, Utah County
Gas
300 MWIn study Utah, UTWest Jun 2023target 2026
Battery storage project J3558, Champaign County
Battery storage
300 MWIn study Champaign, ILMISO Apr 2024target 2027
Jade Meadow III Solar Facility
Solar + storage
300 MWAgreement signed Garrett, MDPJM Sep 2020target 2028
Solar + storage project C1-39, Washington County
Solar + storage · REBU BN, LLC
300 MWAgreement signed Washington, UTWest May 2021target 2027
Solar + storage project Company MH, Churchill County
Solar + storage
300 MWAgreement signed Churchill, NVWest Sep 2021target 2024
Solar project J1214, Dane County
Solar
300 MWAgreement signed Dane, WIMISO Apr 2019target 2025
Onshore wind project G0973, Mason County
Onshore wind
300 MWIn study Mason, WAWest Oct 2023target 2029
SP Jaguar BESS
Other · PP Jaguar BESS LLC
300 MWPaused / redesign Mclennan, TXERCOT Mar 20212025
Onshore wind project J1025, Knox County
Onshore wind
300 MWAgreement signed Knox, MOMISO Mar 2018target 2025
Solar + storage project GEN-2024-336, Yoakum County
Solar + storage
300 MWIn study Yoakum, TXSPP Mar 2025target 2029
Solar + storage project 9, Grant County
Solar + storage
300 MWIn study Grant, WAWest Sep 2023
Battery storage project GEN-2024-SR15, Yoakum County
Battery storage
300 MWIn study Yoakum, TXSPP Oct 2024target 2026
Solar + storage project GI-2025-01, Morgan County
Solar + storage
300 MWIn study Morgan, COWest Apr 2025target 2030
Bellefield 3 Solar Farm
Solar + storage
300 MWAgreement signed Kern, CACAISO Apr 2020target 2027
Page 37 of 184

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)