🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

SOLAR + STORAGE · SPP

Solar + storage project GEN-2024-336, Yoakum County

Solar + storage project GEN-2024-336, Yoakum County is a 300 MW solar + storage request in interconnection study in the SPP interconnection queue, in Yoakum County, Texas, connecting to SPS.

Queue statusIn planning
  1. PlanningQueued Mar 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Apr 2029 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GEN-2024-336
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SPS
Connection point (POI)
Ink Basin 230 kV Substation
Location
Yoakum County, Texas
Technology
Solar: 300 MW · Battery
Total requested
300 MW
Service type
NRIS and ERIS
Study phase
DISIS STAGE
Queue status
Active
Entered queue
1 March 2025
Proposed online date
April 2029

Location

Marker shows the centre of Yoakum County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Yoakum County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem