Gas project GEN-2011-048, Yoakum County

Gas project GEN-2011-048, Yoakum County is a 175 MW gas request built and operating in the SPP interconnection queue, in Yoakum County, Texas, connecting to SPS.

Queue statusOperating
  1. PlanningQueued Sep 2011 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingMar 2013 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
GEN-2011-048
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SPS
Connection point (POI)
Mustang 230kV
Location
Yoakum County, Texas
Technology
Gas: 175 MW
Total requested
175 MW
Service type
NRIS and ERIS
Study phase
IA FULLY EXECUTED/COMMERCIAL OPERATION
Queue status
Operational
Entered queue
30 September 2011
Proposed online date
March 2013
Came online
March 2013

Location

Marker shows the centre of Yoakum County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Yoakum County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem