United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Interconnection queue in the USA — page 95

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown9,1872,001.0 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

9,187 requests · page 95 of 184
ProjectCapacityStatusLocationRegionQueuedOnline
Marshall Spring Solar
Solar + storage · Marshall Springs Solar, LLC
150 MWIn study Gillespie, TXERCOT Feb 2023target 2026
Solar + storage project GI-2023-175, Imperial County
Solar + storage
150 MWIn study Imperial, CAWest Apr 2023target 2028
Solar project IC-989, Johnson County
Solar
150 MWPaused / redesign Johnson, GASoutheast Oct 2021target 2025
Solar + storage project J3745, Dearborn County
Solar + storage
150 MWIn study Dearborn, INMISO Apr 2024target 2028
Wild Grains Solar
Solar
150 MWAgreement signed Van Wert, OHPJM Oct 2019target 2027
Onshore wind project J1967, Champaign County
Onshore wind
150 MWIn study Champaign, ILMISO Mar 2022target 2025
Solar project J1783, Montgomery County
Solar
150 MWIn study Montgomery, INMISO Jun 2020target 2025
Battery storage project J3543, Dakota County
Battery storage
150 MWIn study Dakota, MNMISO Apr 2024target 2028
Photo BESS 2
Solar + storage · CED Development Inc.
150 MWIn study Uvalde, TXERCOT Oct 2021target 2027
Solar project 25-IC-1323, Dodge County
Solar
150 MWIn study Dodge, GASoutheast Apr 2025target 2028
Onshore wind project GEN-2017-086, Harper County
Onshore wind
150 MWAgreement signed Harper, KSSPP May 20172025
Solar project J2740, Sunflower County
Solar
150 MWIn study Sunflower, MSMISO Sep 2022target 2029
Solar project J3844, St. Joseph County
Solar
150 MWIn study St. Joseph, MIMISO Nov 2024target 2029
Battery storage project AI2-071, Atlantic County
Battery storage
150 MWIn study Atlantic, NJPJM Feb 2023target 2027
Solar project J1027, Pike County
Solar
150 MWAgreement signed Pike, INMISO Mar 2018target 2022
Solar project 16-058, Jefferson County
Solar
150 MWPaused / redesign Jefferson, ORWest Jul 2016target 2018
French Creek Solar and BESS
Solar + storage · French Creek Energy, LLC
150 MWAgreement signed Erie, PAPJM Sep 2020target 2029
Battery storage project IC-905, Putnam County
Battery storage
150 MWAgreement signed Putnam, GASoutheast Oct 2020target 2027
Solara BESS 2
Battery storage · CED Development Inc.
150 MWIn study Jones, TXERCOT Jul 2022target 2027
Battery storage project AI2-001, Caroline County
Battery storage
150 MWIn study Caroline, VAPJM Oct 2022target 2028
Solar project J2678, Delta County
Solar
150 MWIn study Delta, MIMISO Sep 2022target 2025
Surplus; J1566
Battery storage
150 MWIn study Martin, MNMISO Jan 2025target 2028
Solar + storage project GEN-2022-111, Marion County
Solar + storage
150 MWIn study Marion, TXSPP Feb 2023target 2027
Battery storage project J3505, Bollinger County
Battery storage
150 MWIn study Bollinger, MOMISO Apr 2024target 2028
Solar + storage project 2022-G11, Maricopa County
Solar + storage
150 MWIn study Maricopa, AZWest Aug 2022target 2025
San Perlita BESS 1
Battery storage · RWE Renewables
150 MWIn study Willacy, TXERCOT Jun 2022target 2025
Solar + storage project J2389, Adams County
Solar + storage
150 MWIn study Adams, ILMISO Sep 2022target 2026
Talbot Solar
Solar
150 MWIn study Talbot, GASoutheast Dec 20212023
Battery storage project J3651, Lenawee County
Battery storage
150 MWIn study Lenawee, MIMISO Apr 2024target 2028
Solar project J2659, Sangamon County
Solar
150 MWIn study Sangamon, ILMISO Oct 2025target 2026
Solar project J1286, Evangeline Parish County
Solar
150 MWUnder construction Evangeline Parish, LAMISO Apr 2019target 2025
Battery storage project GEN-2024-325, Chaves County
Battery storage
150 MWIn study Chaves, NMSPP Mar 2025target 2028
Energy Mountain
Battery storage
150 MWPaused / redesign Bucks, PAPJM Mar 2018target 2029
Battery storage project IA-PNM-2023-18, Valencia County
Battery storage
150 MWIn study Valencia, NMWest Sep 2023target 2026
Solar project J1553, Clinton County
Solar
150 MWAgreement signed Clinton, MIMISO Dec 2021target 2025
Battery storage project 147, Pima County
Battery storage
150 MWIn study Pima, AZWest Dec 2022target 2026
Battery storage project J2731, Olmsted County
Battery storage
150 MWIn study Olmsted, MNMISO Sep 2022target 2025
Solar + storage project J2869, Sunflower County
Solar + storage
150 MWIn study Sunflower, MSMISO Sep 2022target 2027
Solar + storage project J2129, Barry County
Solar + storage
150 MWIn study Barry, MIMISO Aug 2021target 2024
Solar project G0847, Columbia County
Solar
150 MWIn study Columbia, WAWest Feb 2023target 2024
Crossroads Solar
Solar + storage
150 MWIn study Liberty, GASoutheast Jun 2021target 2024
NY Chateaugay 0 Willis Rd Storage (NYISO-C24-304-004)
Battery storage
150 MWIn study Franklin, NYISO-NE Dec 2024target 2028
Solar project J1084, Clinton County
Solar
150 MWUnder construction Clinton, IAMISO Mar 2018target 2023
Onshore wind project C2-49, Converse County
Onshore wind
150 MWIn study Converse, WYWest May 2022target 2026
Battery storage project J3636, Tuscola County
Battery storage
150 MWIn study Tuscola, MIMISO Apr 2024target 2028
Solar + storage project J3733, Gibson County
Solar + storage
150 MWIn study Gibson, INMISO May 2024target 2028
Solar + storage project BHCT G35, Pueblo County
Solar + storage
150 MWIn study Pueblo, COWest Aug 2022target 2026
Solar project J1482, White County
Solar
150 MWAgreement signed White, INMISO Apr 20192024
Solar project GEN-2019-003, Roosevelt County
Solar
150 MWAgreement signed Roosevelt, NMSPP Apr 2019target 2027
Battery storage project AH2-077, Sussex County
Battery storage
150 MWIn study Sussex, DEPJM Jan 2022target 2027
Page 95 of 184

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)