United States › Grid › Interconnection queues › Illinois
ONSHORE WIND · MISOOnshore wind project J1967, Champaign County
Onshore wind project J1967, Champaign County is a 150 MW onshore wind request in interconnection study in the MISO interconnection queue, in Champaign County, Illinois, connecting to AMEREN ILLINOIS.
- PlanningQueued Mar 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Oct 2025 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J1967
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- AMEREN ILLINOIS
- Connection point (POI)
- Rantoul East 138kV
- Location
- Champaign County, Illinois
- Technology
- Wind: 150 MW
- Total requested
- 150 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 2; Post GIA Status: Not Started
- Queue status
- Active
- Entered queue
- 24 March 2022
- Proposed online date
- October 2025
Location
Marker shows the centre of Champaign County; the queue data does not give exact sites.
Other requests in Champaign County
- Solar project J1139, Champaign CountySolar · 150 MW · agreement signed
- Battery storage project J3558, Champaign CountyBattery storage · 300 MW · in study
- Solar project J3353, Champaign CountySolar · 191 MW · in study
- Onshore wind project J3918, Champaign CountyOnshore wind · 138 MW · in study
- Solar + storage project J2648, Champaign CountySolar + storage · 135 MW · in study
- Battery storage project J3565, Champaign CountyBattery storage · 100 MW · in study
- Battery storage project J2124, Champaign CountyBattery storage · 100 MW · in study
- Onshore wind project J3700, Champaign CountyOnshore wind · 300 MW · withdrawn
- Solar project J3520, Champaign CountySolar · 215 MW · withdrawn
- Solar project J1688, Champaign CountySolar · 200 MW · withdrawn
- Solar project J1970, Champaign CountySolar · 160 MW · withdrawn
- Onshore wind project J3483, Champaign CountyOnshore wind · 137 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem