United States › Grid › Interconnection queues › Illinois

ONSHORE WIND · MISO

Onshore wind project J1967, Champaign County

Onshore wind project J1967, Champaign County is a 150 MW onshore wind request in interconnection study in the MISO interconnection queue, in Champaign County, Illinois, connecting to AMEREN ILLINOIS.

Queue statusIn planning
  1. PlanningQueued Mar 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Oct 2025 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J1967
Grid region
MISO (Midcontinent)
Utility / transmission owner
AMEREN ILLINOIS
Connection point (POI)
Rantoul East 138kV
Location
Champaign County, Illinois
Technology
Wind: 150 MW
Total requested
150 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Active
Entered queue
24 March 2022
Proposed online date
October 2025

Location

Marker shows the centre of Champaign County; the queue data does not give exact sites.

Power plants in Illinois · Transmission lines in Illinois

Other requests in Champaign County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem