Solar project J3353, Champaign County

Solar project J3353, Champaign County is a 191 MW solar request in interconnection study in the MISO interconnection queue, in Champaign County, Illinois, connecting to AMEREN TRANSMISSION COMPANY OF ILLINOIS.

Queue statusIn planning
  1. PlanningQueued Apr 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Aug 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J3353
Grid region
MISO (Midcontinent)
Utility / transmission owner
AMEREN TRANSMISSION COMPANY OF ILLINOIS
Connection point (POI)
Rising
Location
Champaign County, Illinois
Technology
Solar: 191 MW
Total requested
191 MW
Service type
Energy only (ERIS)
Study phase
Study Phase: DPP 1
Queue status
Active
Entered queue
18 April 2024
Proposed online date
August 2028

Location

Marker shows the centre of Champaign County; the queue data does not give exact sites.