United States › Grid › Interconnection queues › Louisiana
SOLAR · MISOSolar project J1286, Evangeline Parish County
Solar project J1286, Evangeline Parish County is a 150 MW solar request under construction in the MISO interconnection queue, in Evangeline Parish County, Louisiana, connecting to CLECO POWER.
Queue statusUnder construction
- PlanningQueued Apr 2019 (completed)
- ConsentedNov 2021 (completed)
- Construction (current stage)
- OperatingTarget Apr 2025 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- J1286
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- CLECO POWER
- Connection point (POI)
- Manuel 138 kV Substation
- Location
- Evangeline Parish County, Louisiana
- Technology
- Solar: 150 MW
- Total requested
- 150 MW
- Service type
- Energy only (ERIS)
- Study phase
- Study Phase: GIA Complete; Post GIA Status: Under Construction
- Queue status
- Active
- Entered queue
- 29 April 2019
- Agreement signed
- 29 November 2021
- Proposed online date
- April 2025
Location
Marker shows the centre of Evangeline Parish County; the queue data does not give exact sites.
Other requests in Evangeline Parish County
- Solar project J2322, Evangeline Parish CountySolar · 200 MW · in study
- Solar + storage project J1686, Evangeline Parish CountySolar + storage · 100 MW · in study
- Solar project J1384, Evangeline Parish CountySolar · 200 MW · withdrawn
- Solar project J2135, Evangeline Parish CountySolar · 200 MW · withdrawn
- Solar project J3238, Evangeline Parish CountySolar · 155 MW · withdrawn
- Solar project J1796, Evangeline Parish CountySolar · 150 MW · withdrawn
- Solar project J2467, Evangeline Parish CountySolar · 105 MW · withdrawn
- Battery storage project J2424, Evangeline Parish CountyBattery storage · 100 MW · withdrawn
- Battery storage project J1908, Evangeline Parish CountyBattery storage · 100 MW · withdrawn
- Solar project J2257, Evangeline Parish CountySolar · 80.0 MW · withdrawn
- Battery storage project J1290, Evangeline Parish CountyBattery storage · 25.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem