United States › Grid › Interconnection queues › Louisiana
SOLAR + STORAGE · MISOSolar + storage project J1686, Evangeline Parish County
Solar + storage project J1686, Evangeline Parish County is a 100 MW solar + storage request in interconnection study in the MISO interconnection queue, in Evangeline Parish County, Louisiana, connecting to CLECO POWER.
- PlanningQueued Jul 2022 (current stage)
- ConsentedAug 2025 (not yet reached)
- Construction (not yet reached)
- OperatingTarget Sep 2026 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J1686
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- CLECO POWER
- Connection point (POI)
- Coughlin - Plaisance 138 kV
- Location
- Evangeline Parish County, Louisiana
- Technology
- Solar: 100 MW · Battery
- Total requested
- 100 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA In Process; Post GIA Status: Not Started
- Queue status
- Active
- Entered queue
- 7 July 2022
- Agreement signed
- 18 August 2025
- Proposed online date
- September 2026
Location
Marker shows the centre of Evangeline Parish County; the queue data does not give exact sites.
Other requests in Evangeline Parish County
- Solar project J1286, Evangeline Parish CountySolar · 150 MW · under construction
- Solar project J2322, Evangeline Parish CountySolar · 200 MW · in study
- Solar project J1384, Evangeline Parish CountySolar · 200 MW · withdrawn
- Solar project J2135, Evangeline Parish CountySolar · 200 MW · withdrawn
- Solar project J3238, Evangeline Parish CountySolar · 155 MW · withdrawn
- Solar project J1796, Evangeline Parish CountySolar · 150 MW · withdrawn
- Solar project J2467, Evangeline Parish CountySolar · 105 MW · withdrawn
- Battery storage project J2424, Evangeline Parish CountyBattery storage · 100 MW · withdrawn
- Battery storage project J1908, Evangeline Parish CountyBattery storage · 100 MW · withdrawn
- Solar project J2257, Evangeline Parish CountySolar · 80.0 MW · withdrawn
- Battery storage project J1290, Evangeline Parish CountyBattery storage · 25.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem