United States › Grid › Interconnection queues › Minnesota
BATTERY STORAGE · MISOSurplus; J1566
Surplus; J1566 is a 150 MW battery storage request in interconnection study in the MISO interconnection queue, in Martin County, Minnesota, connecting to SOUTHERN MINNESOTA MUNICIPAL POWER AGENCY.
Queue statusIn planning
- PlanningQueued Jan 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jul 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- S1080
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- SOUTHERN MINNESOTA MUNICIPAL POWER AGENCY
- Connection point (POI)
- Rutland
- Location
- Martin County, Minnesota
- Technology
- Battery: 150 MW
- Total requested
- 150 MW
- Queue status
- Active
- Entered queue
- 14 January 2025
- Proposed online date
- July 2028
Location
Marker shows the centre of Martin County; the queue data does not give exact sites.
Other requests in Martin County
- Solar project J1566, Martin CountySolar · 150 MW · in study
- Onshore wind project G164, Martin CountyOnshore wind · 200 MW · built
- Onshore wind project G263, Martin CountyOnshore wind · 105 MW · built
- Onshore wind project G386, Martin CountyOnshore wind · 100 MW · built
- Other project G741, Martin CountyOther · 8.0 MW · built
- Other project G319, Martin CountyOther · 2.0 MW · built
- Gas project J3547, Martin CountyGas · 630 MW · withdrawn
- Onshore wind project J671, Martin CountyOnshore wind · 400 MW · withdrawn
- Onshore wind project H005, Martin CountyOnshore wind · 300 MW · withdrawn
- Onshore wind project G770, Martin CountyOnshore wind · 100 MW · withdrawn
- Onshore wind project H043, Martin CountyOnshore wind · 50.0 MW · withdrawn
- Onshore wind project G797, Martin CountyOnshore wind · 30.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem