United States β€Ί Grid β€Ί Interconnection queues β€Ί Minnesota

ONSHORE WIND Β· MISO

Onshore wind project J671, Martin County

Onshore wind project J671, Martin County is a 400 MW onshore wind request withdrawn in the MISO interconnection queue, in Martin County, Minnesota.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2016 (completed)
  2. Withdrawn / abandonedJun 2017 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J671
Grid region
MISO (Midcontinent)
Connection point (POI)
Unknown
Location
Martin County, Minnesota
Technology
Wind: 400 MW
Total requested
400 MW
Study phase
Feasibility
Queue status
Withdrawn
Entered queue
11 July 2016
Proposed online date
September 2019
Withdrawn
June 2017

Location

Marker shows the centre of Martin County; the queue data does not give exact sites.

Power plants in Minnesota Β· Transmission lines in Minnesota

Other requests in Martin County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem