Onshore wind project G263, Martin County

Onshore wind project G263, Martin County is a 105 MW onshore wind request built and operating in the MISO interconnection queue, in Martin County, Minnesota.

Queue statusOperating
  1. PlanningQueued Oct 2002 (completed)
  2. ConsentedMay 2005 (completed)
  3. Construction (completed)
  4. OperatingNov 2007 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
G263
Grid region
MISO (Midcontinent)
Connection point (POI)
Lakefield Generating Substation
Location
Martin County, Minnesota
Technology
Wind: 105 MW
Total requested
105 MW
Study phase
Network Upgrade
Queue status
Operational
Entered queue
22 October 2002
Agreement signed
24 May 2005
Proposed online date
November 2007
Came online
November 2007

Location

Marker shows the centre of Martin County; the queue data does not give exact sites.

Power plants in Minnesota · Transmission lines in Minnesota

Other requests in Martin County