GAS Β· MISOGas project J3547, Martin County
Gas project J3547, Martin County is a 630 MW gas request withdrawn in the MISO interconnection queue, in Martin County, Minnesota, connecting to NORTHERN STATES POWER COMPANY.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2024 (completed)
- Withdrawn / abandonedDec 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J3547
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- NORTHERN STATES POWER COMPANY
- Connection point (POI)
- LAKEFIELD
- Location
- Martin County, Minnesota
- Technology
- Gas: 630 MW
- Total requested
- 630 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 1
- Queue status
- Withdrawn
- Entered queue
- 17 April 2024
- Proposed online date
- June 2026
- Withdrawn
- December 2025
Location
Marker shows the centre of Martin County; the queue data does not give exact sites.
Power plants in Minnesota Β· Transmission lines in Minnesota
Other requests in Martin County
- Surplus; J1566Battery storage Β· 150 MW Β· in study
- Solar project J1566, Martin CountySolar Β· 150 MW Β· in study
- Onshore wind project G164, Martin CountyOnshore wind Β· 200 MW Β· built
- Onshore wind project G263, Martin CountyOnshore wind Β· 105 MW Β· built
- Onshore wind project G386, Martin CountyOnshore wind Β· 100 MW Β· built
- Other project G741, Martin CountyOther Β· 8.0 MW Β· built
- Other project G319, Martin CountyOther Β· 2.0 MW Β· built
- Onshore wind project J671, Martin CountyOnshore wind Β· 400 MW Β· withdrawn
- Onshore wind project H005, Martin CountyOnshore wind Β· 300 MW Β· withdrawn
- Onshore wind project G770, Martin CountyOnshore wind Β· 100 MW Β· withdrawn
- Onshore wind project H043, Martin CountyOnshore wind Β· 50.0 MW Β· withdrawn
- Onshore wind project G797, Martin CountyOnshore wind Β· 30.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem