United States β€Ί Grid β€Ί Interconnection queues β€Ί Minnesota

ONSHORE WIND Β· MISO

Onshore wind project H043, Martin County

Onshore wind project H043, Martin County is a 50.0 MW onshore wind request withdrawn in the MISO interconnection queue, in Martin County, Minnesota.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2008 (completed)
  2. Withdrawn / abandonedMar 2010 (project stopped here)
  3. ConsentedMar 2010 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
H043
Grid region
MISO (Midcontinent)
Connection point (POI)
ITC Midwest Truman 69 kV Substation
Location
Martin County, Minnesota
Technology
Wind: 50.0 MW
Total requested
50.0 MW
Study phase
SPA - SIS
Queue status
Withdrawn
Entered queue
12 June 2008
Agreement signed
29 March 2010
Proposed online date
June 2012
Withdrawn
March 2010

Location

Marker shows the centre of Martin County; the queue data does not give exact sites.

Power plants in Minnesota Β· Transmission lines in Minnesota

Other requests in Martin County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem