🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Minnesota

ONSHORE WIND · MISO

Onshore wind project G164, Martin County

Onshore wind project G164, Martin County is a 200 MW onshore wind request built and operating in the MISO interconnection queue, in Martin County, Minnesota.

Queue statusOperating
  1. PlanningQueued Feb 2003 (completed)
  2. ConsentedOct 2005 (completed)
  3. Construction (completed)
  4. OperatingDec 2006 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
G164
Grid region
MISO (Midcontinent)
Connection point (POI)
Lakefield Junction 345 kV substation
Location
Martin County, Minnesota
Technology
Wind: 200 MW
Total requested
200 MW
Study phase
Network Upgrade
Queue status
Operational
Entered queue
18 February 2003
Agreement signed
1 October 2005
Proposed online date
December 2006
Came online
December 2006

Location

Marker shows the centre of Martin County; the queue data does not give exact sites.

Power plants in Minnesota · Transmission lines in Minnesota

Other requests in Martin County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem