🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Michigan

SOLAR + STORAGE · MISO

Solar + storage project J2129, Barry County

Solar + storage project J2129, Barry County is a 150 MW solar + storage request in interconnection study in the MISO interconnection queue, in Barry County, Michigan, connecting to WOLVERINE POWER SUPPLY COOPERATIVE.

Queue statusIn planning
  1. PlanningQueued Aug 2021 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Apr 2024 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J2129
Grid region
MISO (Midcontinent)
Utility / transmission owner
WOLVERINE POWER SUPPLY COOPERATIVE
Connection point (POI)
Bradley 138 kV Substation
Location
Barry County, Michigan
Technology
Solar: 150 MW · Battery
Total requested
150 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 3; Post GIA Status: Not Started
Queue status
Active
Entered queue
26 August 2021
Proposed online date
April 2024
Withdrawn
September 2023

Location

Marker shows the centre of Barry County; the queue data does not give exact sites.

Power plants in Michigan · Transmission lines in Michigan

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem