United States › Grid › Interconnection queues › Texas
SOLAR + STORAGE · SPPSolar + storage project GEN-2022-111, Marion County
Solar + storage project GEN-2022-111, Marion County is a 150 MW solar + storage request in interconnection study in the SPP interconnection queue, in Marion County, Texas, connecting to AEP.
Queue statusIn planning
- PlanningQueued Feb 2023 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Apr 2027 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- GEN-2022-111
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Wilkes 345 kV Substation
- Location
- Marion County, Texas
- Technology
- Solar: 150 MW · Battery
- Total requested
- 150 MW
- Service type
- NRIS and ERIS
- Study phase
- FACILITY STUDY STAGE
- Queue status
- Active
- Entered queue
- 10 February 2023
- Proposed online date
- April 2027
Location
Marker shows the centre of Marion County; the queue data does not give exact sites.
Other requests in Marion County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem