United States › Grid › Interconnection queues › Texas

SOLAR + STORAGE · SPP

Solar + storage project GEN-2024-122, Marion County

Solar + storage project GEN-2024-122, Marion County is a 160 MW solar + storage request in interconnection study in the SPP interconnection queue, in Marion County, Texas, connecting to AEP.

Queue statusIn planning
  1. PlanningQueued Mar 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Oct 2029 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GEN-2024-122
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
AEP
Connection point (POI)
Lieberman - IPC Jefferson 138 kV Line
Location
Marion County, Texas
Technology
Solar: 160 MW · Battery
Total requested
160 MW
Service type
NRIS and ERIS
Study phase
DISIS STAGE
Queue status
Active
Entered queue
1 March 2025
Proposed online date
October 2029

Location

Marker shows the centre of Marion County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Marion County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem