🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Interconnection queue in the USA — page 75

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown9,1872,001.0 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

9,187 requests · page 75 of 184
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project J3440, Daviess County
Battery storage
200 MWIn study Daviess, MOMISO Apr 2024target 2028
Solar project J1684, Starke County
Solar
200 MWIn study Starke, INMISO Aug 2023target 2029
Solar project IC-1094, Irwin County
Solar
200 MWAgreement signed Irwin, GASoutheast Nov 2022target 2028
Onshore wind project J4129, Otter Tail County
Onshore wind
200 MWIn study Otter Tail, MNMISO Oct 2025target 2029
Battery storage project Company 220, Clark County
Battery storage
200 MWPaused / redesign Clark, NVWest Mar 2022target 2029
Battery storage project GEN-2018-028, Tulsa County
Battery storage
200 MWAgreement signed Tulsa, OKSPP May 2018target 2028
Blooming Grove Solar Energy Center
Solar
200 MWAgreement signed Livingston, ILPJM Sep 2018target 2028
Solar project J3522, Cass County
Solar
200 MWIn study Cass, NDMISO Mar 2024target 2028
Solar + storage project T2-024, Klamath County
Solar + storage
200 MWIn study Klamath, ORWest Sep 2025target 2026
Solar project J1062, Washtenaw County
Solar
200 MWAgreement signed Washtenaw, MIMISO Mar 2018target 2023
Solar + storage project Company 192, Clark County
Solar + storage
200 MWAgreement signed Clark, NVWest Sep 2020target 2024
Rodeo Solar
Solar · Core Solar SPV I, LLC
200 MWAgreement signed Andrews, TXERCOT Jun 2017target 2026
Solar + storage project J3879, Jackson County
Solar + storage
200 MWIn study Jackson, INMISO May 2024target 2030
Solar + storage project Company LC, Lander County
Solar + storage
200 MWPaused / redesign Lander, NVWest Mar 2021target 2029
Geothermal project 25-00410, Humboldt County
Geothermal
200 MWIn study Humboldt, NVWest Jul 2025target 2031
Battery storage project J3298, Tazewell County
Battery storage
200 MWIn study Tazewell, ILMISO Apr 2024target 2027
Solar + storage project Q442, Yuma County
Solar + storage
200 MWIn study Yuma, AZWest Mar 2022target 2026
LD200SB
Solar + storage
200 MWIn study Luna, NMWest Jun 2025target 2028
Battery storage project J4019, Calhoun County
Battery storage
200 MWIn study Calhoun, MIMISO May 2025target 2030
Onshore wind project GEN-2017-144, Holt County
Onshore wind
200 MWAgreement signed Holt, NESPP Nov 2017target 2028
Solar project J1558, Pope County
Solar
200 MWIn study Pope, ARMISO Jun 2020target 2026
Onshore wind project G0819, Douglas County
Onshore wind
200 MWIn study Douglas, WAWest Nov 2022target 2027
NY125C - Little Salmon Solar
Solar · Little Salmon Solar LLC
200 MWIn study Franklin, NYNYISO Aug 2024target 2028
Solar + storage project IC-1042, Rockdale County
Solar + storage
200 MWPaused / redesign Rockdale, GASoutheast Jul 2022target 2026
Battery storage project S0017, Iron County
Battery storage
200 MWIn study Iron, UTWest Dec 2022target 2026
Battery storage project IA-PNM-2023-03, Bernalillo County
Battery storage
200 MWIn study Bernalillo, NMWest Dec 2023target 2027
Battery storage project J1894, Kalamazoo County
Battery storage
200 MWIn study Kalamazoo, MIMISO Oct 2021target 2024
Solar + storage project IA-PNM-2023-05, Bernalillo County
Solar + storage
200 MWIn study Bernalillo, NMWest Jan 2023target 2027
Solar project J3959, Grundy County
Solar
200 MWIn study Grundy, MOMISO Apr 2025target 2029
Surplus; J992
Battery storage
200 MWIn study Cass, INMISO Jun 2025target 2026
Anson Solar Center, Phase III
Solar · Anson Solar Center 3, LLC
200 MWIn study Jones, TXERCOT Jun 2017target 2027
Battery storage project GEN-2022-024, Bourbon County
Battery storage
200 MWIn study Bourbon, KSSPP Jun 2022target 2028
Solar + storage project 666, Canyon County
Solar + storage · Powers Butte Energy Center, LLC
200 MWPaused / redesign Canyon, IDWest Aug 2022target 2026
Solar + storage project J3058, Arkansas County
Solar + storage
200 MWIn study Arkansas, ARMISO Jul 2025target 2025
Onshore wind project J2930, Henderson County
Onshore wind
200 MWIn study Henderson, KYMISO Sep 2022target 2025
Solar project J1306, Perry County
Solar
200 MWAgreement signed Perry, ILMISO Apr 2019target 2024
Battery storage project GEN-2024-SR6, Johnston County
Battery storage
200 MWIn study Johnston, OKSPP Feb 2024
Wind + storage project J3122, Crittenden County
Wind + storage
200 MWIn study Crittenden, ARMISO Sep 2022target 2025
Other project 109, Pima County
Other · TEP
200 MWIn study Pima, AZWest Dec 2021target 2024
Solar project 20190729002, Colleton County
Solar
200 MWIn study Colleton, SCSoutheast target 2022
Solar project IC-868, Bartow County
Solar
200 MWAgreement signed Bartow, GASoutheast May 2020target 2028
Geothermal project 25-00408, Churchill County
Geothermal
200 MWIn study Churchill, NVWest Jul 2025target 2033
Millers Branch Solar I
Solar · Miller's Branch Solar, LLC
200 MWAgreement signed Haskell, TXERCOT Dec 2019target 2025
Battery storage project J3784, Ozaukee County
Battery storage
200 MWIn study Ozaukee, WIMISO Apr 2024target 2028
Avocet Storage
Battery storage
200 MWAgreement signed Los Angeles, CACAISO Apr 2019target 2026
Solar project J4090, Schuyler County
Solar
200 MWIn study Schuyler, MOMISO Oct 2025target 2030
Battery storage project 21-099, Washington County
Battery storage
200 MWAgreement signed Washington, ORWest May 2021target 2027
Battery storage project 429, Clay County
Battery storage
200 MWAgreement signed Clay, MSSoutheast Apr 2020target 2028
Solar + storage project Company LY, Eureka County
Solar + storage
200 MWPaused / redesign Eureka, NVWest Sep 2021target 2025
Battery storage project 121, Pinal County
Battery storage
200 MWIn study Pinal, AZWest May 2022target 2026
Page 75 of 184

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)