SOLAR · SOUTHEASTSolar project IC-1094, Irwin County
Solar project IC-1094, Irwin County is a 200 MW solar request with a signed interconnection agreement in the Southeast interconnection queue, in Irwin County, Georgia, connecting to Southern Company.
Queue statusConsented
- PlanningQueued Nov 2022 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Jun 2028 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- IC-1094
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Southern Company
- Connection point (POI)
- North Tifton - Stump Creek 230 kV Line
- Location
- Irwin County, Georgia
- Technology
- Solar: 200 MW
- Total requested
- 200 MW
- Service type
- Energy only (ERIS)
- Study phase
- IA Executed
- Queue status
- Active
- Entered queue
- 22 November 2022
- Proposed online date
- June 2028
Location
Marker shows the centre of Irwin County; the queue data does not give exact sites.
Other requests in Irwin County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem