United States › Grid › Interconnection queues › Georgia
SOLAR · SOUTHEASTOcilla Solar
Ocilla Solar is a 150 MW solar request in interconnection study in the Southeast interconnection queue, in Irwin County, Georgia, connecting to Georgia Transmission.
Queue statusIn planning
- PlanningQueued Nov 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Nov 2025 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- GI-170
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Georgia Transmission
- Connection point (POI)
- Lake Beatrice - Stump Lake 115 kV TL
- Location
- Irwin County, Georgia
- Technology
- Solar: 150 MW
- Total requested
- 150 MW
- Study phase
- Facilities Study
- Queue status
- Active
- Entered queue
- 30 November 2022
- Proposed online date
- November 2025
Location
Marker shows the centre of Irwin County; the queue data does not give exact sites.
Other requests in Irwin County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem