BATTERY STORAGE · MISOSurplus; J992
Surplus; J992 is a 200 MW battery storage request in interconnection study in the MISO interconnection queue, in Cass County, Indiana, connecting to DUKE ENERGY INDIANA.
Queue statusIn planning
- PlanningQueued Jun 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jun 2026 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- S1102
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- DUKE ENERGY INDIANA
- Connection point (POI)
- Walton 230
- Location
- Cass County, Indiana
- Technology
- Battery: 200 MW
- Total requested
- 200 MW
- Queue status
- Active
- Entered queue
- 16 June 2025
- Proposed online date
- June 2026
Location
Marker shows the centre of Cass County; the queue data does not give exact sites.
Other requests in Cass County
- Solar project J992, Cass CountySolar · 200 MW · under construction
- Gas project G299, Cass CountyGas · 4.0 MW · built
- Onshore wind project X1-020, Cass CountyOnshore wind · 1,500 MW · withdrawn
- Solar project J1741, Cass CountySolar · 270 MW · withdrawn
- Solar + storage project J3016, Cass CountySolar + storage · 150 MW · withdrawn
- Solar project J1680, Cass CountySolar · 100 MW · withdrawn
- Battery storage project J1692, Cass CountyBattery storage · 65.0 MW · withdrawn