United States βΊ Grid βΊ Interconnection queues βΊ Indiana
SOLAR + STORAGE Β· MISOSolar + storage project J3016, Cass County
Solar + storage project J3016, Cass County is a 150 MW solar + storage request withdrawn in the MISO interconnection queue, in Cass County, Indiana, connecting to DUKE ENERGY INDIANA.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2022 (completed)
- Withdrawn / abandonedOct 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J3016
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- DUKE ENERGY INDIANA
- Connection point (POI)
- Walton
- Location
- Cass County, Indiana
- Technology
- Solar: 150 MW Β· Battery
- Total requested
- 150 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 2; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 14 September 2022
- Proposed online date
- June 2027
- Withdrawn
- October 2025
Location
Marker shows the centre of Cass County; the queue data does not give exact sites.
Other requests in Cass County
- Solar project J992, Cass CountySolar Β· 200 MW Β· under construction
- Surplus; J992Battery storage Β· 200 MW Β· in study
- Gas project G299, Cass CountyGas Β· 4.0 MW Β· built
- Onshore wind project X1-020, Cass CountyOnshore wind Β· 1,500 MW Β· withdrawn
- Solar project J1741, Cass CountySolar Β· 270 MW Β· withdrawn
- Solar project J1680, Cass CountySolar Β· 100 MW Β· withdrawn
- Battery storage project J1692, Cass CountyBattery storage Β· 65.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem