United States › Grid › Interconnection queues › Indiana

SOLAR · MISO

Solar project J992, Cass County

Solar project J992, Cass County is a 200 MW solar request under construction in the MISO interconnection queue, in Cass County, Indiana, connecting to DUKE ENERGY INDIANA.

Queue statusUnder construction
  1. PlanningQueued Mar 2018 (completed)
  2. ConsentedOct 2021 (completed)
  3. Construction (current stage)
  4. OperatingTarget Oct 2023 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
J992
Grid region
MISO (Midcontinent)
Utility / transmission owner
DUKE ENERGY INDIANA
Connection point (POI)
Walton 230kV Substation
Location
Cass County, Indiana
Technology
Solar: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Under Construction
Queue status
Active
Entered queue
12 March 2018
Agreement signed
12 October 2021
Proposed online date
October 2023

Location

Marker shows the centre of Cass County; the queue data does not give exact sites.

Power plants in Indiana · Transmission lines in Indiana

Other requests in Cass County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem