United States › Grid › Interconnection queues › Kentucky
ONSHORE WIND · MISOOnshore wind project J2930, Henderson County
Onshore wind project J2930, Henderson County is a 200 MW onshore wind request in interconnection study in the MISO interconnection queue, in Henderson County, Kentucky, connecting to Southern Indiana Gas & Electric Company d/b/a Centerpoint Energy Indiana South.
- PlanningQueued Sep 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Oct 2025 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J2930
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- Southern Indiana Gas & Electric Company d/b/a Centerpoint Energy Indiana South
- Connection point (POI)
- AB Brown 345 - Reid EHV (BREC Terminal) 345.0kV
- Location
- Henderson County, Kentucky
- Technology
- Wind: 200 MW
- Total requested
- 200 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 2; Post GIA Status: Not Started
- Queue status
- Active
- Entered queue
- 14 September 2022
- Proposed online date
- October 2025
Location
Marker shows the centre of Henderson County; the queue data does not give exact sites.
Other requests in Henderson County
- Solar project J1466, Henderson CountySolar · 250 MW · agreement signed
- Solar project J2931, Henderson CountySolar · 400 MW · in study
- Battery storage project J2844, Henderson CountyBattery storage · 200 MW · in study
- Solar project J1696, Henderson CountySolar · 150 MW · in study
- Solar project J1604, Henderson CountySolar · 50.0 MW · in study
- Other project G108, Henderson CountyOther · 1,000 MW · withdrawn
- Gas project LGE-GIS-2007-004, Henderson CountyGas · 642 MW · withdrawn
- Coal project J237, Henderson CountyCoal · 642 MW · withdrawn
- Gas project LGE-GIS-2007-003, Henderson CountyGas · 640 MW · withdrawn
- Coal project R44, Henderson CountyCoal · 485 MW · withdrawn
- Solar project J1886, Henderson CountySolar · 300 MW · withdrawn
- Solar project J2225, Henderson CountySolar · 300 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem