United States › Grid › Interconnection queues › Kentucky

SOLAR · MISO

Solar project J1696, Henderson County

Solar project J1696, Henderson County is a 150 MW solar request in interconnection study in the MISO interconnection queue, in Henderson County, Kentucky, connecting to BIG RIVERS ELECTRIC CORPORATION.

Queue statusIn planning
  1. PlanningQueued Jun 2020 (current stage)
  2. ConsentedJun 2025 (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J1696
Grid region
MISO (Midcontinent)
Utility / transmission owner
BIG RIVERS ELECTRIC CORPORATION
Connection point (POI)
Reid EHV 161kV
Location
Henderson County, Kentucky
Technology
Solar: 150 MW
Total requested
150 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA In Process; Post GIA Status: Not Started
Queue status
Active
Entered queue
11 June 2020
Agreement signed
25 June 2025
Proposed online date
June 2026

Location

Marker shows the centre of Henderson County; the queue data does not give exact sites.

Power plants in Kentucky · Transmission lines in Kentucky

Other requests in Henderson County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem