United States β€Ί Grid β€Ί Interconnection queues β€Ί Kentucky

OTHER Β· MISO

Other project G108, Henderson County

Other project G108, Henderson County is a 1,000 MW other request withdrawn in the MISO interconnection queue, in Henderson County, Kentucky.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2001 (completed)
  2. Withdrawn / abandonedMay 2003 (project stopped here)
  3. ConsentedMay 2003 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G108
Grid region
MISO (Midcontinent)
Connection point (POI)
Unknown
Location
Henderson County, Kentucky
Technology
Other: 1,000 MW
Total requested
1,000 MW
Queue status
Withdrawn
Entered queue
6 July 2001
Agreement signed
27 May 2003
Proposed online date
June 2004
Withdrawn
May 2003

Location

Marker shows the centre of Henderson County; the queue data does not give exact sites.

Power plants in Kentucky Β· Transmission lines in Kentucky

Other requests in Henderson County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem