GAS Β· SOUTHEASTGas project LGE-GIS-2007-004, Henderson County
Gas project LGE-GIS-2007-004, Henderson County is a 642 MW gas request withdrawn in the Southeast interconnection queue, in Henderson County, Kentucky, connecting to Louisville Gas & Electric and Kentucky Utilities Energy.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2007 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- LGE-GIS-2007-004
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Louisville Gas & Electric and Kentucky Utilities Energy
- Connection point (POI)
- Daviess 345 kV substation bus
- Location
- Henderson County, Kentucky
- Technology
- Gas: 642 MW Β· Coal
- Total requested
- 642 MW
- Service type
- Network resource (NRIS)
- Queue status
- Withdrawn
- Entered queue
- 24 April 2007
- Proposed online date
- March 2011
Location
Marker shows the centre of Henderson County; the queue data does not give exact sites.
Other requests in Henderson County
- Solar project J1466, Henderson CountySolar Β· 250 MW Β· agreement signed
- Solar project J2931, Henderson CountySolar Β· 400 MW Β· in study
- Onshore wind project J2930, Henderson CountyOnshore wind Β· 200 MW Β· in study
- Battery storage project J2844, Henderson CountyBattery storage Β· 200 MW Β· in study
- Solar project J1696, Henderson CountySolar Β· 150 MW Β· in study
- Solar project J1604, Henderson CountySolar Β· 50.0 MW Β· in study
- Other project G108, Henderson CountyOther Β· 1,000 MW Β· withdrawn
- Coal project J237, Henderson CountyCoal Β· 642 MW Β· withdrawn
- Gas project LGE-GIS-2007-003, Henderson CountyGas Β· 640 MW Β· withdrawn
- Coal project R44, Henderson CountyCoal Β· 485 MW Β· withdrawn
- Solar project J1886, Henderson CountySolar Β· 300 MW Β· withdrawn
- Solar project J2225, Henderson CountySolar Β· 300 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem